New Path - Unbound Surface
This is an old version of the page
Date published: 14 May, 2021
Date superseded: 18 February, 2022
For recent changes to this guidance, please see the bottom of the page.
Aim
The aim of this item is to construct a new path for non-motorised public use, with a hard-core sub base and a whin-dust or equivalent surface, to provide a robust and comfortable path for shared use.
Eligibility
Any land is eligible.
Requirements
If ground is hard and well drained, construct standard 'full tray' path:
- dig out and establish a rectangular section 'full tray' to at least 100mm depth
- fill with Type 1 hard-core sub-base material 100mm minimum depth and compact with a vibrating plate or roller
- apply a surface layer of whin dust, granite dust or equivalent to a minimum depth of 25mm, and compact with a vibrating plate or roller
- re-use excavated spoil to landscape path edges and verges
If ground is soft, deep mud/peat and/or poorly drained, construct a ‘half-tray’ with geotextile path:
- dig out and establish a rectangular section path tray at least 50mm deep, using excavated spoil to build up the path edge and verge
- line tray with geotextile and/or geo-grid if on deep soft wet ground
- fill with Type 1 hard-core base material 100mm minimum depth and compact with vibrating plate or roller
- apply a surface layer of whin dust, granite dust or equivalent to a minimum depth of 25mm, and compact with a vibrating plate or roller
If ground contains tree roots or bedrock, construct a “floating” path:
- establish a rectangular section ‘floating tray’ to at least 100mm depth, using spoil and turf to create a path edge and verge
- line tray with geo-textile if required to protect tree roots
- fill with Type 1 hard-core sub-base material 100mm minimum depth and compact with a vibrating plate or roller
- apply a surface layer of whin dust, granite dust or equivalent to a minimum depth of 25mm, and compact with a vibrating plate or roller
Other details:
- path width will normally be 1.8 metres
- depending on anticipated user numbers, mix of user types, flow and terrain narrower or wider path may be acceptable if justified, within the range of 1.2m to 2.5m
- photographic evidence: You must keep a photographic record of the path construction showing before and during construction and to include the following:
- Tray creation and excavation: clearly showing 100mm depth, photos taken at intervals along path length
- Sub-base laying and compaction : photos showing compaction in process
- Surface material laying; clearly showing 25mm depth, photos taken at intervals along path length.
Payment
You can claim £18.20 per square metre.
Inspections
The inspectors will check:
- the location and extent of the work as is detailed in the contract schedule of works and contract map
- That the capital item requirements have been met as detailed above
- That photographic evidence has been provided as detailed above
Recent changes
Section | Change |
---|---|
Whole page | Relfection of 2021 round |
Previous versions
Download guidance
Click 'Download this page' to create a printable version of this guidance you can save or print out.